Detailed view of all 20 masterplan initiatives and their 30 tracks — Q4 2026

15 Total12 In progress0 Completed3 Not started15 Fully funded0 Partially funded0 Unfunded8 Multi-DP
PILLARINITIATIVEPARTNERFUNDINGSTATUSPROGRESSDetails
Pillar 1
I3: Development of a harmonised intra-regional cross-border mobile money/ e-wallet regulatory framework
TWG 1 · Q3 2026–Q4 2027 · 18 months · Est. USD 400,000
GIZ / BMZFully fundedIn progress
Behind: 2 overdue
20%
expected 60%
Pillar 2
I10.1: Develop national retail instant switches for all Partner States ★ Multi-DP · 2
TWG 2 · Q3 2026–Q3 2029 · 39 months · Est. USD 500,000
GIZ / BMZ, FSD NetworkFully fundedNot started
0%
expected 0%
Pillar 2
I10.2: Develop a common rulebook for cross-border retail payments ★ Multi-DP · 2
TWG 2 · Q3 2025–Q4 2028 · 42 months · Est. USD 200,000
GIZ / BMZ, FSD NetworkFully fundedIn progress
Behind: 1 overdue
25%
expected 50%
Pillar 2
I10.3: Interlink existing national retail switches ★ Multi-DP · 3
TWG 2 · Q2 2025–Q4 2029 · 57 months · Est. USD 500,000
World Bank Group, FSD Network, GIZ / BMZFully fundedIn progress
17%
expected 17%
Pillar 2
I10.4: Transition to a fit-for-purpose regional centralised switch ★ Multi-DP · 3
TWG 2 · Q3 2026–Q4 2030 · 54 months · Est. USD 10,500,000
World Bank Group, GIZ / BMZ, FSD NetworkFully fundedIn progress
25%
expected 25%
Pillar 3
I12: Constitution of a regional payments system forum which includes private sector participation ★ Multi-DP · 2
TWG 3 · Q3 2026–Q4 2026 · 6 months · Est. USD 200,000
GIZ / BMZ, FSD NetworkFully fundedIn progress
Behind: 1 overdue
67%
expected 100%
Pillar 3
I14.1: Quick Response (QR) code for simplified user experiences and alignment of risk management of QR transactions
TWG 3 · Q3 2026–Q3 2028 · 27 months · Est. USD 200,000
GIZ / BMZFully fundedIn progress
Behind: 1 overdue
20%
expected 40%
Pillar 3
I14.2: Proxy identifiers/ aliases and their validation processes
TWG 3 · Q3 2026–Q3 2028 · 27 months · Est. USD 200,000
GIZ / BMZFully fundedIn progress
25%
expected 25%
Pillar 3
I14.3: Open and secure APIs for seamless technical integration and onboarding
TWG 3 · Q3 2026–Q3 2028 · 27 months · Est. USD 200,000
GIZ / BMZFully fundedIn progress
Behind: 1 overdue
25%
expected 50%
Pillar 3
I15.1: Define a regional KPI framework aligned with the G20 principles ★ Multi-DP · 2
TWG 3 · Q4 2025–Q1 2031 · 66 months · Est. USD 100,000
Gates Foundation, GIZ / BMZFully fundedIn progress
Behind: 4 overdue
38%
expected 88%
Pillar 4
I16.1: Build capacity on CBDC
TWG 3 · Q3 2026–Q3 2030 · 51 months · Est. USD 100,000
GIZ / BMZFully fundedIn progress
38%
expected 0%
Pillar 4
I16.2: Assess feasibility of CBDCs for cross-border payments
TWG 3 · Q3 2026–Q4 2027 · 18 months · Est. USD 250,000
GIZ / BMZFully fundedIn progress
50%
expected 50%
Pillar 4
I18: Explore the use of emerging technologies and schemes in the context of payments
TWG 3 · Q3 2026–Q3 2030 · 51 months · Est. USD 300,000
GIZ / BMZFully fundedNot started
0%
expected 0%
Pillar 4
I19: Promote regional payment systems through awareness and dissemination ★ Multi-DP · 3
TWG 3 · Q3 2026–Q2 2031 · 60 months · Est. USD 890,000
AfDB, GIZ / BMZ, FSD NetworkFully fundedNot started
0%
expected 0%
Pillar 4
I20: Enhance knowledge of payment systems through knowledge sharing and peer learning ★ Multi-DP · 2
TWG 3 · Q3 2026–Q2 2031 · 60 months · Est. USD 1,590,000
GIZ / BMZ, FSD NetworkFully fundedIn progress
0%
expected 0%

The black tick on each bar marks where the initiative is expected to be by now: the share of its activities whose target date has passed.

Figures for Q4 2026, published 2026-10-30 04:18+03:00 EAT by the EAC Secretariat from the Masterplan Reporting Tool. Progress = weighted share of activities Done (Reporting Tool method). Each initiative is shown as last reported at or before this quarter. Download the initiative figures (CSV)